Nanyang 10-Ton Medical Waste Treatment Equipment Installed and Now in Use

Time:

On July 1, 2026, a 10-ton medical waste treatment equipment system arrived at a treatment factory in Nanyang, China. Installation and debugging were completed, and the equipment has been put into use.

The system processes 10 tons of medical waste per day and is now operating in the factory. Our engineers handled on-site installation and commissioning, and the line started operation on schedule.

Key Facts

  • Capacity: 10 tons per day
  • Date: July 1, 2026
  • Location: Nanyang, China
  • Status: installed and in use

The Nanyang project adds reliable, high-capacity treatment capability to the region and reflects our experience in delivering complete medical waste treatment solutions from delivery to start-up.